MP-023  /  Example project  /  Education

Secondary school science block

Six laboratories, a prep room and the connecting corridor, rebuilt across two holiday windows, with teaching spaces released in phases so the school keeps running.

Sector
Education
Location
London
Type
Example project

Illustration of a refurbished school science block

MP-050 / Brief

The brief

A 1970s science block with failing services, no fume extraction to current standards, and a corridor that could not take the year-group movement it was carrying.

A typical school has one fixed constraint: the block had to be teaching on the first day of the autumn term. Practical completion was therefore a date, not a target, and the programme was built backwards from it with float held against the risks flagged at tender.

Work like this starts with a measured survey and an itemised quotation.

MP-051 / Scope

What we delivered

  • Six laboratories stripped to structure and rebuilt, including benching, services and fume extraction.
  • New prep room with dedicated chemical storage and separate extract.
  • Corridor widened, requiring new structural openings and supporting steelwork.
  • Full mechanical and electrical replacement, including new distribution boards and LED throughout.
  • Fire compartmentation upgraded and fire doors replaced, certificated at handover.
  • Windows replaced across the elevation, with improved acoustic performance.
  • Flooring, ceilings and decoration throughout the block.

MP-052 / Challenges

Three problems we plan for

01 / Drainage

Below-slab drainage was not where the record drawings said

Older blocks rarely match their record drawings. We hold float against this risk and re-sequence around it rather than extend the programme.

Any variation priced and agreed before work proceeds.

02 / Occupation

The block stayed partly in use through the summer term

Two laboratories were released on a rota rather than all six at once, behind a hoarded and dust-sealed line, with noisy work confined to agreed windows.

Noisy work confined to agreed windows.

03 / Steelwork

The corridor openings needed temporary works over a live route

Propping is designed, installed and inspected out of hours, so the route stays open on teaching days.

Structural openings formed out of hours.

Scaffold and hoarding segregating the works from the live school route
Illustration · Segregation to the live route
Replacement windows to the science block elevation
Illustration · Elevation, windows replaced
Completed laboratory with new benching and services
Illustration · Laboratory, complete

MP-053 / Outcome

Ready for the first day of term

The aim is a block that is teaching on the first day of term, with snagging closed out promptly and a 12-month defects period.